Purchase Requests (PR) and Approvals in Tonbab

A purchase request (PR) is where purchasing starts in Tonbab. The requester creates and submits it, procurement finds vendors and prices, an approver approves it, and Tonbab generates one purchase order (PO) per vendor.

Create a purchase request

  1. Go to Operation › Purchasing › Purchase Requests and click New Purchase Request.
  2. Pick the Account Assignment:
    • Job / Project: the cost goes to a job control.
    • Stock Replenishment: buying into stock.
    • Expense: general purchases.
  3. Add lines with Add Line or Add multiple. For labour or contracted work, tick Service / labor. If an item has a bill of materials, click Expand BOM to replace it with its components.
  4. Click Create PR (Draft), then Submit when it's ready.

The list page also has Review shortages (materials a work order ran short of) and Consolidate demand to combine demand from several sources into one PR.

Steps and statuses

Status Who does what Button
Draft Requester edits and submits Submit
Submitted Procurement picks it up Start Review
Under Procurement Review Procurement sets a vendor and price on every line Complete Sourcing
Pending Approval Approver decides Approve / Reject
Approved Procurement creates POs Generate POs
Rejected Sent back for changes Reopen for Resourcing / Revert to Draft

Once POs are created, the status becomes Partially Converted or Fully Converted. Generate POs creates one draft PO per vendor. If other approved PRs have lines for the same vendor, a Consolidate with {n} other PR(s) button lets you combine them into one PO.

The Approvals page

Approvers see everything waiting for them under Approvals in the sidebar. It brings together PRs that are Pending Approval, PR / PO revert requests, delivery note reversal requests, and leave, overtime and expense claims.

Auto-approve (optional)

A company can let PRs below a set ceiling approve themselves. It's off by default. In strict mode, every line must also have a preferred vendor with a valid agreed price in THB.

Changes after approval and re-approval

You can still edit an approved PR that has no PO yet, but Tonbab sends it back to Pending Approval when:

  • lines are added, removed or substituted, or
  • the total rises above the tolerance (10% by default, set per company).

The PR shows This request was revised and needs re-approval, and the requester is notified. To swap an item for a substitute, use the This line replaces (substitution) field in the edit form. The line then shows Replaces #{n} {item} so the approver can see the change clearly.

Document chain lock

Once a PO is made from a PR, the PR is locked. To change it, delete the PO (and any goods receipts on it) first. People who can't revert directly see Request Revert instead, which sends a request to the Approvals page.

Next steps